Rehabilitation of Al-Anaz Bridge in Al Anbar Governorate
            
                Scope of Work :
                
                    
                        Al-Anaz Bridge was bombed and destroyed by terrorist acts, which resulted in the destruction of five sections of the bridge with a total length of 150 m. This project is deemed to be one of the projects of the Emergency Development Operations Project in Iraq submitted by the Ministry of Construction and Housing. The work method includes preparations, demolition and removal of rubble for five sections, processing of damaged concrete parts, concrete works, manufacture of iron joists for the bridge and complementary works.
                    
                    
					  
					  
                            Project Location : Al Anbar City
                            
                            Contract Value (US$) : 2,598,250	
                            Contract Duration : 350 days
                            Contract Start Date : 20/ Oct / 2018 
                            Contract Completion : 20/ Oct / 2019